From The Manifesto of February 10, 2008:
Acerra incinerator Affairs
Survey. The
Fibe wanted to gain from energy production. A business worth millions of euro. Burning everything, even the tires. Here's what lies behind the construction.
Fibe wanted to gain from energy production. A business worth millions of euro. Burning everything, even the tires. Here's what lies behind the construction.
Francesca Pilla
Naples
incinerate everything, all the garbage in Campania, plastic, paper, glass, aluminum, and why not, even tires. Solid waste incinerators, power generation and earn billions of euro, with the guarantee of having a monopoly for at least 16 years, but through the "moves" just to get to a quarter of a century and beyond. This would be the goal-Fibe Impregilo, not two and a half billion euro served in 14 years to maintain standing charges for the bandwagon of the police special. The golden advice, salaries millionaires Antonio Bassolino, the deputy Raffaele Vanoli of subcommissario Facchi Julius (who deny having met with astonishing figures) are a story within a story, if there have been only partly explain the environmental disaster. May be the reason for the consent to a proposed "affordable", where even the "recommended" are part of the system. But how and why you get irreparable in the management system, now in the hands of the prefect De Gennaro, called for business leaders and Impregilo had a name: the Acerra incinerator. In order to construct it - according to surveys of pm Giuseppe Noviello and Paul Sirleo - Pier Giorgio Romiti head Impregilo, Paolo Romiti Fibe commercial director of the subsidiary, other executives Armando Cattaneo and Vincenzo Urciuoli, along with the cdr capimpianto cheated, bypassed, worked under the table with hope-the only guarantee that the project went to successful. No one would have to find that the product was not in accordance with cdr, who had not declared the possession of the landfill at the time of the race, which had not landed with the shipping costs of ecoballe outside the region (as well as in the contract). Once turned on those blessed furnaces Acerra, mountains of waste would have evaporated in the ashes (also toxic). Maybe they also received the congratulations of the government and Government's duty to have put an end to the cyclical crises bells. Certainly would have gained over the years astronomical. And the commissioner Bassolino? For the prosecution would have facilitated the operations and given different, too, go ahead and exit "safe."
E 'was the inquiry by the prosecutor of Naples to avoid the inevitable. Three years of investigations which have produced over 100 000 pages of cases and 29 defendants. One hundred folders full of meticulous steps, documents, wiretaps, make up a construct confirmed last summer by the investigating magistrate Rosanna Saraceno, who ordered the seizure of € 750 million and the company prohibited the participation of public tenders for waste disposal. Now hearing Preliminary charges of seeking to confirm the points: they have cheated the Campania region and the government for private interests. The Camorra is not about a tube in slow agony that led to the collapse of the entire cycle. Even if it was infiltrated in the various processes, its role was marginal.
As you wander the contract
The tender of '99 was clear and without loopholes. The Impregilo was to build the incinerator within 14 months, have available land and facilities operated by law, in particular with the Law of '98. He could not subcontract to third parties any of the activities, including transport, especially in case of malfunction or slippage of time should have incur any expenditure on the transport of ecoballe outside the region. All rejected. The multinational would have lied from the beginning, without having participated in half of the requirements, among other things, engaging in an activity that had nothing to do with his experience in construction. As confirmed by the facts, the Impregilo-Fisia-Fibe has not complied with any of the requirements, even when she realized that the cycle organized the scam would not work, trying to gain on the disasters. And 'here Bassolino and his staff were engaged in a pattern of abuse from 2001 to 2004, and that exceptions to the fundamental points of agreement. It was not within the powers of the police the ability to change the race procurement to help foster the company. The Commissioner would authorize, without having the power, the "creation" of the lay-bys for ecoballe: monsters like the citadel of the "rubbish" at Taverna del Re di Giugliano, Villa Literno, Santa Maria La Fossa. Not only that, you incur the costs of disposal and failure can not be 'controlled' cdr plants. If it went really well what's going on? There have been bypassed or earned? The courts will decide.
Banks knew?
engineers and consultants, but they had proof that the system was "fake." They are, in fact, before the lending banks to make that something is wrong. In 2001 the San Paolo Imi bank group and the International West LB, the demand for large funds want to see us send a clear and consultant, engineer Paul Polinelli of Montgomery Watson. Despite attempts to disguise and analysis of "domesticated" by the laboratory Fisia of Genoa, Polinelli considered inadequate facilities. Proceed to new controls and how am told he concludes: "Our analysis of the project was gradually relieved from analysis on cdr ... far higher than was deemed absolutely required. " But Armando Cattaneo, former CEO of Fibe, who allegedly knew and shared with the supervision of Pier Giorgio Romiti, given all the reassurances adaptation. The parties are a "ruse", as reported Polinelli: "The average cdr would comply with the contractual parameters. Before entering into financing in 2003, therefore, a "side letter Cdr 'where you provide any adjustments. Only the Credit Lyonnaise had already marched, had probably smelled "burnt." On the phone, in May 2004, the same Cattaneo says that while banks were aware of the problems on the quality of cdr 'Commissioner (Bassolino, ed) had a mild approach. " Later, with the facilities that made the water Fibe decides to "go further" and open dumps ghost they will not be closing the valves by banks.
No separate, more energy
In 2002, however, the situation began to plummet, from right to left in parliament calling on behalf of rubbish in the street by two parliamentary questions Emidio Novi (Fi) and Pecoraro Scanio (Greens ). In August 2002, Cattaneo writes a note to the CDM "to resolve any doubt 'means the material is usually cites controls Fisia of Genoa. Since it was also the go-ahead dell'Arpac, so it is suspected the manager Maurizio Avallone, despite surveys that had never complained of irregularities. Commissioner Bassolino is the intermediary with the government and manage to steal several OPCM to face the perpetual emergency. Raining money, derogations, special powers. Plans for the separation, however, did not take off. The reasons are different. In 2005 on the user in use Figliola Ettore, a lawyer of the civil protection department, explains it this way: "You might not have understood a bat ... have created a society that has made contracts to give it a. .. (Unintelligible) ... of the entire property of the municipality of Naples. Bassolino and Co. made a tender for the collection, the beauty of spending 280 billion, have since bought a set of means and autocompattattori for normal rubbish? Once in Asia have given him free loan. In short, the Commissioner understands the media, gives them to someone, someone creates a society ... worse. " But this is an assumption the limits of the Ill, not a test.
To the accusation is instead a fact that Impregilo had an interest in putting everything in the incinerator to earn more and also lost time because of the protests of Acerra, the requirements and governmental investigations. In fact, the judges, with several parallel investigations begin gradually to seize the plants considered old and inadequate, blocking a cycle "artificial." Not to blame because the machinery could not even store the aluminum and plastic waste had more output than the entrance of talquale, as confirmed even by a Fibe technician, engineer Sergio Pomodoro. Not only that. Ecoballe we also ended up in the tires, which would increase the energy produced by incineration. Here is what we read in the Acts: 'Performing recovery of special waste, used tires, with high calorific value for the increase of the PCI all'additivazione prodromal bales Cdr. The technical Fibe writes in time to all officers Impregilo to ask the necessary adjustments to the law. On 10.16.2002, in particular, refers to the internal test sites Caivano and Giugliano. "While those Caivano - he writes - are considered to be positive on average (except for the chlorine content) than those Giugliano are considered unsatisfactory." Tomatoes also claims that it is a generalized condition because "the separation efficiency of the plants are substantially different from those of the project (ie it all together: plastic paper, ferrous metals, ndr)" and that it must be adjusted. Today, after six years, quell'adeguamento is still a dead letter.
E 'was the inquiry by the prosecutor of Naples to avoid the inevitable. Three years of investigations which have produced over 100 000 pages of cases and 29 defendants. One hundred folders full of meticulous steps, documents, wiretaps, make up a construct confirmed last summer by the investigating magistrate Rosanna Saraceno, who ordered the seizure of € 750 million and the company prohibited the participation of public tenders for waste disposal. Now hearing Preliminary charges of seeking to confirm the points: they have cheated the Campania region and the government for private interests. The Camorra is not about a tube in slow agony that led to the collapse of the entire cycle. Even if it was infiltrated in the various processes, its role was marginal.
As you wander the contract
The tender of '99 was clear and without loopholes. The Impregilo was to build the incinerator within 14 months, have available land and facilities operated by law, in particular with the Law of '98. He could not subcontract to third parties any of the activities, including transport, especially in case of malfunction or slippage of time should have incur any expenditure on the transport of ecoballe outside the region. All rejected. The multinational would have lied from the beginning, without having participated in half of the requirements, among other things, engaging in an activity that had nothing to do with his experience in construction. As confirmed by the facts, the Impregilo-Fisia-Fibe has not complied with any of the requirements, even when she realized that the cycle organized the scam would not work, trying to gain on the disasters. And 'here Bassolino and his staff were engaged in a pattern of abuse from 2001 to 2004, and that exceptions to the fundamental points of agreement. It was not within the powers of the police the ability to change the race procurement to help foster the company. The Commissioner would authorize, without having the power, the "creation" of the lay-bys for ecoballe: monsters like the citadel of the "rubbish" at Taverna del Re di Giugliano, Villa Literno, Santa Maria La Fossa. Not only that, you incur the costs of disposal and failure can not be 'controlled' cdr plants. If it went really well what's going on? There have been bypassed or earned? The courts will decide.
Banks knew?
engineers and consultants, but they had proof that the system was "fake." They are, in fact, before the lending banks to make that something is wrong. In 2001 the San Paolo Imi bank group and the International West LB, the demand for large funds want to see us send a clear and consultant, engineer Paul Polinelli of Montgomery Watson. Despite attempts to disguise and analysis of "domesticated" by the laboratory Fisia of Genoa, Polinelli considered inadequate facilities. Proceed to new controls and how am told he concludes: "Our analysis of the project was gradually relieved from analysis on cdr ... far higher than was deemed absolutely required. " But Armando Cattaneo, former CEO of Fibe, who allegedly knew and shared with the supervision of Pier Giorgio Romiti, given all the reassurances adaptation. The parties are a "ruse", as reported Polinelli: "The average cdr would comply with the contractual parameters. Before entering into financing in 2003, therefore, a "side letter Cdr 'where you provide any adjustments. Only the Credit Lyonnaise had already marched, had probably smelled "burnt." On the phone, in May 2004, the same Cattaneo says that while banks were aware of the problems on the quality of cdr 'Commissioner (Bassolino, ed) had a mild approach. " Later, with the facilities that made the water Fibe decides to "go further" and open dumps ghost they will not be closing the valves by banks.
No separate, more energy
In 2002, however, the situation began to plummet, from right to left in parliament calling on behalf of rubbish in the street by two parliamentary questions Emidio Novi (Fi) and Pecoraro Scanio (Greens ). In August 2002, Cattaneo writes a note to the CDM "to resolve any doubt 'means the material is usually cites controls Fisia of Genoa. Since it was also the go-ahead dell'Arpac, so it is suspected the manager Maurizio Avallone, despite surveys that had never complained of irregularities. Commissioner Bassolino is the intermediary with the government and manage to steal several OPCM to face the perpetual emergency. Raining money, derogations, special powers. Plans for the separation, however, did not take off. The reasons are different. In 2005 on the user in use Figliola Ettore, a lawyer of the civil protection department, explains it this way: "You might not have understood a bat ... have created a society that has made contracts to give it a. .. (Unintelligible) ... of the entire property of the municipality of Naples. Bassolino and Co. made a tender for the collection, the beauty of spending 280 billion, have since bought a set of means and autocompattattori for normal rubbish? Once in Asia have given him free loan. In short, the Commissioner understands the media, gives them to someone, someone creates a society ... worse. " But this is an assumption the limits of the Ill, not a test.
To the accusation is instead a fact that Impregilo had an interest in putting everything in the incinerator to earn more and also lost time because of the protests of Acerra, the requirements and governmental investigations. In fact, the judges, with several parallel investigations begin gradually to seize the plants considered old and inadequate, blocking a cycle "artificial." Not to blame because the machinery could not even store the aluminum and plastic waste had more output than the entrance of talquale, as confirmed even by a Fibe technician, engineer Sergio Pomodoro. Not only that. Ecoballe we also ended up in the tires, which would increase the energy produced by incineration. Here is what we read in the Acts: 'Performing recovery of special waste, used tires, with high calorific value for the increase of the PCI all'additivazione prodromal bales Cdr. The technical Fibe writes in time to all officers Impregilo to ask the necessary adjustments to the law. On 10.16.2002, in particular, refers to the internal test sites Caivano and Giugliano. "While those Caivano - he writes - are considered to be positive on average (except for the chlorine content) than those Giugliano are considered unsatisfactory." Tomatoes also claims that it is a generalized condition because "the separation efficiency of the plants are substantially different from those of the project (ie it all together: plastic paper, ferrous metals, ndr)" and that it must be adjusted. Today, after six years, quell'adeguamento is still a dead letter.